To minimize the impact on businesses and allow for annual downtown events to take place, work will take place in three (3) phases as follows:
- Phase 1 - (April 17 - June 15): North side of St. Charles Rd. from Elizabeth St. to Main St.
- Phase 2 (June 16 - August 27): North side of St. Charles Rd. from Main St. to Craig Place
- Phase 3 (August 28- October 29): South side of St. Charles Rd. from Elizabeth St. to Garfield St.
Pending weather and unforeseen circumstances, all work should be complete by the end of November 2023.