2019 Asphalt Paving & Patching

General Information

Tentative Start Date: June 2019
Tentative Completion Date: August 2019
Project Manager: Tom Dixon
Contractor: Schroeder Asphalt Services, Inc.
Awarded Contract Amount: $1,415,003.61
Funding Source(s): Motor Fuel Tax and Capital Improvements

Contact Information

Public Works Department
Phone: (630) 620-5740
Email: publicworks@villageoflombard.org

Project Manager: Tom Dixon
Phone: (630) 620-5740
Email: dixont@villageoflombard.org

After Hours: Lombard Police Department
Phone: (630) 873-4400 

Communications

Notify Me: Residents and businesses within construction areas are encouraged to sign up for Notify Me to receive timely updates regarding construction in their area. 

Newsletters: Periodically, newsletters and notices will be distributed to residents to keep them apprised of current and upcoming construction related events.

6/20/19 - Newsletter No. 1

FAQs

How does this benefit the Village? When completed, drivability and drainage will be improved.

Will my road be closed? There should be no road closures due to this project.

If my driveway is inaccessible where do I park? Residents whose driveways are impacted by the construction will receive prior notice and parking permits allowing overnight parking on the street for the duration of their driveway closure.

Will my water or sewer service be affected? Water and sewer service will not be affected by this project. 

Project Information

This Project Includes: Milling and resurfacing of selected streets; concrete removal and replacement work as needed, which will primarily be spot curb replacement and sidewalk removal with ADA (American Disability Act) improvements at intersections, patching of utility repairs and parkway restoration.

Project Limits: Various streets throughout the Village that include:

Ann Street - Finley to Dead End EastQueensbury Court - Valley to Cul-de-sac
Ash Street - Elizabeth to MainRegency Drive - Majestic Drive W to Majestic Drive E
Elizabeth Street - Harrison to GrahamRochelle Terrace - LeMoyne to Goebel
Fairfield Avenue - 18th to 22ndRoyal Drive - Majestic to Cul-de-sac
Foxworth Blvd. - I-355 Bridge to FinleySheila Place - Lemoyne to Goebel
Garfield Terrace - Dead End North to 440 S. Garfield TerraceSpringer Drive - Oak Creek to Foxworth
Goebel Drive - Ridge to MainStewart - Madison to Harrison
Greenfield Avenue - West Road to MainValley Road - Foxworth to Village Limits
LeMoyne Avenue - Ridge to MainWashington Blvd. - Craig to Grace
Lloyd Avenue - Foxworth to Village LimitsWaters Edge - Cul-de-sac to Springer
Majestic Drive - Main to HighlandWitt Court - Cul-de-sac to Valley
Oak Creek Drive - I-355 Bridge to Finley

 

Full depth patching will be done at the following locations:

580 Waters Edge2 W. St. Charles Road
Westmore & St. Charles Rd. Intersection10 W. St. Charles Road
162 S. Grace Street18 W. St. Charles Road
60 N. Columbine (Route 53)28 W. St. Charles Road


Traffic Impact: Moderate for those streets being resurfaced. Temporary one-lane traffic situations will occur during grinding and paving operations.