Concrete Rehabilitation & Utility Cuts Patching

General Information

 
Start Date: April 17, 2017
Tentative Completion Date: Mid-August
Bid Date: 03/14/2017
Bid Award: 04/06/2017
Project Manager: Ray Hoving
Contractor: Schroeder & Schroeder
Awarded Contract Amount: $524,950.00 
Funding Sources: Construction Fund 

Project Information


Project Limits:
Clarendon Ave- Pleasant Ln. to dead end
Kramer Ave- Pleasant Ln. to View St.
Alley- South Broadway to Chase
Alley- South Broadway to Chase to Division
Village wide Patching 

This Project Includes: The removal of the existing concrete street and replacing with new concrete curb and gutter and new concrete roadway. Also included is upgrading driveways, deteriorated sidewalk, crosswalks to meet current ADA standards, and all other necessary improvements needed to complete the above named street repairs.

Project Schedule: April 17 to August 31

Traffic Impact: This project will have a minimal impact on the general motoring public, however, residents of affected streets will be greatly impacted by the work being done. Alternate routes are encouraged for non-residents. No detours will be posted as part of this work.

Contact Information

 
Public Works Department
Phone: (630) 620-5740
Email: publicworks@villageoflombard.org

Project Manager: Ray Hoving
Phone: (630) 620-5740
Email: Hovingr@villageoflombard.org

After Hours: Lombard Police Department
Phone: (630) 873-4400

Communications

 
Notify Me: Residents within construction areas are encouraged to sign up for Notify Me to receive timely updates regarding construction in their area. Click here to sign up.

Newsletters & Notices: Periodically newsletters and notices are distributed to residents to keep them apprised of current and upcoming construction related events.

4/11/17    Newsletter #1 (Highland Avenue & Alleys)

FAQs


How does this benefit me?
The proposed project will improve the drainage and drivability of the impacted streets

Will my road be closed?
The roads in this year’s project will be closed to through traffic however, they will have one lane of traffic open at all times for residents, emergency personnel, deliveries, and garbage and mail service.

If my driveway is inaccessible where do I park?
Residents whose driveways are impacted by the construction will receive parking passes that will allow them to park overnight on side streets for the duration of their driveway closure. 

Will my water or sewer service be affected?
Water and sewer service will not be affected by this project