North Broadway Force Main & Pump Station

North Broadway Forcemain with Aerials

General Information

 
Tentative Start Date: Late July, 2017 
Tentative Completion Date: December 31, 2017 
Project Manager: Ying L. Miao
Bid Opening: March 24, 2017
Bid Award: May 4, 2017
Contractor: Glenbrook Excavating & Concrete, Inc.
Awarded Contract Amount: $1,687,459.50
Funding Sources: Capital Improvements Fund

Project Information


Project Limits: E. North Broadway from Fairfield to S. Grace St; S. Grace Street from E. North Broadway to E. Hickory

This Project Includes: Installation of a pump station at E. North Broadway and Fairfield. It also includes installation of a 30” force main.

Traffic Impact:
No roadway closures or detour are anticipated. The sidewalk on the east side of Grace from North Broadway to Hickory will be closed.
   

Contact Information


Public Works Department
Phone: (630) 620-5740
Email: publicworks@villageoflombard.org
 
Project Manager: Ms. Ying Miao
Phone: (630) 620-5740
Email: miaoy@villageoflombard.org
 
After Hours: Lombard Police Department
Phone: (630) 620-5740

FAQs


Why is this project necessary?
The installation of the pump station and force main is necessary to separate combined sewers located within the Gatz Pond watershed. 
 
How does this benefit the Village?
The project will reduce backyard flooding problem in the Gatz Pond watershed areas due to the sewer backups.
 
Will my driveway be inaccessible?
Driveways along the east side of Grace from North Broadway to Hickory will not be accessible Monday through Friday, 7:00 AM to 4:00 PM during the installation of the force main along Grace.

Will my water be affected? 
There will be no scheduled water service interruptions.

Communications


Public Meeting: May 25, 2017  Presentation
Press Release: June 7, 2017
 
Notify Me: Residents within construction areas are encouraged to sign up for Notify Me to receive timely updates regarding construction in their area. Click here to sign up.

Newsletters & Notices: Periodically newsletters and notices are distributed to residents to keep them apprised of current and upcoming construction related events.

8-11-17  Grace Street Construction Notice


Construction Updates

 

8/8/17 - The contractor is now mobilizing to construct the pump station and force main. Pending adverse weather and other unforeseen delays, the force main pipes will be staged on the south parkway along North Broadway on Wednesday, 8/9. Excavation at the east side of Grace Street for auger pits will take place on August 11th, following by installation of the force main starting August 14th.

Grace Street traffic will be shifted for the construction between Hickory and North Broadway starting on August 14th. Two-way traffic will be maintained but the west side of Grace will be posted “no parking”.

Eastbound North Broadway will be closed during construction starting the week of August 14th. Westbound traffic will be maintained through the entire construction period.

7/18/17 - The project delay has been due to the need to relocate overhead wires and also to receive the 30-in pipe for the force main. The work on the pump station on North Broadway will begin as soon as ComEd and Comcast raise their wires, which is anticipated by the end of July. The force main on Grace will start after the 30-in pipe is delivered, which anticipated in September.